Использование грозозащитного троса в качестве резервной фазы на воздушных линиях электропередачи

Д. С. Левин, А. В. Карнаух, D A Vyrykhanov et al. · Вестник Саратовского государственного технического университета · 2010

Using of a ground wire, as reserve phase, to phase fuse of glaze-wind depositions on overhead transmission lines allowing performing the fuse of the depositions not disconnecting line gave an opportunity of saving power consumers supply. In program Matlab (Simulink) was developed electrodynamics simulation model of overhead transmission lines and was analyzed parameters of power system, when we use of the hawser, as reserve phase.

Cited by 0 works.

Authors