상수도관 전기방식 설계 및 시공에 관한 연구

고지훈, 김병직, 추연길 et al. · 대한전기학회 학술대회 논문집 · 2010

Soil resistivity measured by 4-electrode method of Changwon was estimated to be a suitable for the deepwell method. But in order to meet the projected cathode protection current, the actual high resistivity increase the number of hole and bed, and construction cost will be greatly increased. So in this paper not only presents many problems of the deepwell method but also suggests an optimal design and construction method.

Cited by 0 works.