이동식 임목파쇄기 시공능력 산정 개선방안
안방률, 태용호 · 한국건축시공학회 학술.기술논문발표회 논문집 · 2012
Although work-efficiency of construction machinery is a critical factor for estimating its workable-quantity per unit time, the coefficient figure table presented in the Poom-Sam that is used for Construction Cost Estimation of public sectors in Korea is very subjective for practical usage. In order to suggest objective work-coefficient table for a Tub Grinder, domestic and overseas documentary records were investigated and on-going construction sites were also visited. The research found that the table can be revised by means of detailing down by several factors. The research will be the foundation for applying the rapid development of Construction Equipment and technology to the appropriate cost estimations and the ground work of related studies.