하상변동에 의한 교각세굴 보강에 관한 기초적 연구

서성탁 · 환경관리학회지 · 2014

In order to prevent scouring-related damage under flood condition, bridge pier structures are inspected to judge whether or not repairs or remolding are required. This paper is described for the estimation of scour depth around piers and theoretical review of reinforced method. As the result, free · board and planning flood water level of the river due to the reinforcement of the bridge was investigated 0.44m. It is a insufficient margin to take into takes into account the maximum flood water level. Type selection of the superstructure work is necessary to ensure the margin height corresponding to the frequency plan. Block scour preventive work considering economy and safety are required.