벽식구조 건축물의 공기단축을 위한 거푸집시스템
김동완, 박송우, 이현수 et al. · 대한건축학회 학술발표대회(창립60주년 기념) 논문집 · 2005
Although framework takes 3 days per a floor recently in the construction of high-rise building(over 40 floors), it takes 8-10 days per a floor in the middle-rise(20-40 floors) and wall systems buildings. The reason is that the inside form is used work type by man power although the outside form is large size system form vertical moved by crane or machine. Because inside form is necessary to set up, strip and carry by man power-although it is used system form in the outside, the effect for reducing construction time is less. Therefore, the objective of this study is to propose system wall form for reducing the construction duration by pouring concrete wall and downer slab at the same time. This method is enable to use tower crane for vertical moving inside wall form. As result, this form is enable mechanization and simplification in the form work and realizing 3 days cycle per a floor of framework in the wall systems buildings.