지반굴착에 따른 철도시설물의 침하 원인 및 보강 사례연구

오병삼 · 2012

Recent development trend of construction projects in the urban area is the efficient use of insufficient land, however caused to difficult construction conditions because of many adjacent structures. This paper presents the case study that analyzed the ground settlement of railroad structure for the double track railway project of Gyeongui line, adjacent to the high rise building under ground excavating for substructure work, considering interaction of soft ground characteristics. Field survey and measurement works were carried out during construction of station and excavation of high rise building, and field data were analyzed to find the source of settlement of platform and railway. In addition, the soil reinforcement and foundation restoration were performed using in-situ injection method, i.e., D-ROG(Digitalized Restoring On Grout) method which filled the pore of bottom and around of foundation with micro-cement.

Cited by 0 works.

Authors