초고층 공사 적층공법의 공기지연 방지를 위한 최적 추가자원 계획

최민지, 박문서, 이현수 et al. · 대한건축학회 학술발표대회 논문집 - 구조계 · 2011

Layer construction method which performs structure, exterior, interior activity simultaneously is used in a high-rise building project for effective time management but since a number of activities are being done in parallel, interference and delay are likely to occur. This problem affects on subsequent activities and entire project schedule. Late delivery of curtain wall units is one of the most common reasons for this interference in exterior activity, and more resources are added for finishing works in order to overcome the problems. Since time overrun of the project and new resource input is directly related to project finance, it needs to be managed carefully to avoid excessive expense. In this research, discrete event simulation process of resource optimization to complete project within schedule constraints is developed when time-overrun is expected in a high-rise project using layered construction method, and this can be used in a construction site with its condition applied.

Cited by 0 works.

Authors