건설 시뮬레이션을 활용한 공동주택 골조공사의 생산성 분석에 관한 연구
강동완, 심재규, 김윤겸 et al. · 대한건축학회 논문집 - 구조계 · 2010
Since the frame work of multi-housing projects is not only repetitive construction process, but also critical path in scheduling, the schedule estimation of it has been dealt with a crucial factor for contractors and project managers. In this study, therefore, a simulation model for frame work of multi-housing construction was developed in order to forecast the construction duration of it, based on the CYCLONE method which is one of the widely used simulation technique in the construction field. For developing the model, the detailed literature review and case study were also conducted. As a result of simulation, the developed model could estimate the construction duration of frame work, as well as calculate the construction productivity. Finally, the optimized resource information and equivalent construction duration, which were deduced by the sensitivity analysis through implementing the developed model, could be helpful with the project manager or contractor.