프리캐스트 바닥판 PSC 합성거더 교량의 연속화
정철헌, 현병학 · 2007
In this Paper, a new concept as PnP (precast Slab& Prestressed Concrete Girder) bridge system which uses precast slabs is suggested. This concept is that prestressed concrete girders have non-composite precast slabs during 2nd-prestressing after then precast slabs composite with prestressed concrete girders. Designed by the proposed design equation of a new shear connection, two span continuous beam (17 m@2=34 m) was fabricated to verify constructability and structural safety. A static test was performed to evaluate continuity at diaphragms and the negative moment region cracking. PnP bridge system show : Does not exceed design stresses during construction staging, confirms full composite action in continuous region and safety of negative crack moment. Fast and easy construction would be achieved using the suggested PnP bridge system
Cited by 0 works.