진도~제주간 HVDC연계사업 해저케이블 보호공법 소개
Jong Seok Lee, 문봉수, 송삼섭 et al. · 대한전기학회 학술대회 논문집 · 2009
KEPCO signed up with LS CABLE as a contractor for HVDC submarine cable construction in February 2009. The desk research has been completed in may 2009. Also, Cable route and the protection method will be selected by November 2009. The tentative cable route between Jindo and Jeju which is consisted of sea farms and shipping route zone will reach almost 105㎞. The oceanographic survey for the selection of protection method will be carried out and the survey lists are consisted of MBES, SSS, CPT, ADSP. The protection methods such as burial, Concrete Mattress, UP Pipe, Rock Berm will be selected as per each condition of sea area after the oceanographic survey is completed. Kepco has developed variable methods based on the maintenance experience for HVDC submarine cable between HAENAM and JEJU. Based on the such a accumulated know-how, it can be expected for the confidence and stability of the 2nd HVC project to be improved.