건설공사 공기지연 영향분석을 통한 책임일수 산정체계 구축방안

강인석, 권중희 · 2008

Recently, construction projects are being gradually changed to large projects with complicated work processes. As a result, claims are increasing as well. Of these, the claims by delayed construction duration are given much weight in the general construction claims. To solve this problem, researches to estimate damages due to delay are carried out in research institutes by analyzing the causes of schedule delay. A system to easily estimate responsible days by analyzing the complicated processes needs for project manager. This study suggests a methodology based on the time impact analysis method, which can utilize the consequential analytical method with the consideration of reduced construction period. The suggested methodology is verified by comparing with actual data of case study by the computerized system for estimating the responsible days.

Cited by 0 works.