대단면 장대터널 공기단축 사례연구
노상림, 노승환, 이상필 et al. · 터널과 지하공간 · 2005
The Sapaesan tunnel, the longest twin tube tunnel (4㎞) in Korea with 4 lanes each, is under construction with two years of delayed schedule because of the strong opposition from environmental bodies. Therefore, maximizing the construction efficiency was needed in tunnel project to compensate for time delay. This study includes improvements in the construction of the Sapaesan tunnel such as increasing excavation length and changing excavation sequence. In this paper the system for predicting tunnel face ahead is also introduced. Bulk-Emulsion explosive and Cylinder-Cut method were adopted in tunnel blasting to increase the excavation length. Optimum tunnel excavation step was designed to make up delayed time. Tunnel face mapping, TSP survey and geological prediction system using computerized jumbo-drill were performed for safe construction of long and large twin tube tunnel.