공동주택 터파기 및 지정공사의 적정공기 산정을 위한 비작업일 산정기준과 비작업일수에 관한 연구
방종대, Sang-Hun Song, 조건희 et al. · 대한건축학회 논문집 - 구조계 · 2015
Non-working day in the construction work is closely related with the construction duration and one of the most important factors in the process planning. Although most construction companies in domestic can accurately calculate working days, these companies are difficult to calculate exactly days of non-working because the calculation standard of non-working day is insufficient. Although previous studies have suggested the calculation standard of non-working day due to weather conditions, these studies didnt provide a standard to determine whether the next day is working day or non-working day when it had much rain and snow. In this study, we proposed the new calculation standards of non-working day and days of non-working of 30 cities about the excavation and foundation works. The results of this study will be useful to estimate the proper construction duration for 30 cities. Also, these will be utilized to find start time for the profiTable construction duration in the same project of the same area. Finally, The results of this study will be helped to save construction cost and improve quality of apartment housing.
Cited by 0 works.