사무용건물에서 지열히트펌프냉난방시스템의 운전성능 평가
안형준, 백성권, 조정식 et al. · 2007
For the perfomance test of geothermal system, a large pilot of capacity of 50RT is built and operated in office building. This system is planed hybrid system with cooling tower as asisstance heat sink. From October, 2004 to September, 2005, this system is operated and monitored. As the result, COP of heating periods is about 3.46 and COP of cooling periods is about 4.1. Therefore, geothermal system is useful and suitable in Korea.