도시철도 영업운행선의 궤도개량공사 서행구간 속도향상 연구

김효산, 이창헌, 유재광 et al. · 한국철도학회 학술발표대회논문집 · 2012

During the condition of temporary track support system which is installed when replacing existing ballast tracks to concrete slab tracks on operating line of urban railway, slow train speed shall be applied in order to secure the safe train operation and the quality assurance of poured concrete by restricting train speed as 40km/h for peak hours and 30km/h for non-peak hours. There have been frequent complaints from passengers due to difficulty to satisfy the train headway of 2.5 minutes during morning peak hours. In this study, the safety of temporary track support system has been evaluated which is used during track improvement work to speed up for the section with slow speed and to support track track frame after removal of existing ballast track. And, the improvement method for temporary track support system has been studied by simulating speedup model of train speed through structural analysis for support material based on applying different train speeds.