Daegu metro 3rd line is the first monorail made for public transport in Korea and it is scheduled to open in 2014. A straddle-beam type monorail and HITACH Large type vehicle have been selected for the 3rd line. An Arch Pylon Cable Stayed Bridge has been designed and constructed to across Man-pyeung intersection where two 8 lane roads cross. The Arch Pylon was made of steel and total span length of the bridge is 146.25m. A steel rail beam is used as bridge girder and it is connected to the Pylon by lateral beam. Detail construction stage analysis has been conducted to ensure high accuracy required for monorail system. Also, an influence matrix method has been used to consider effect of cable tensioning to adjacent cables and camber. Additional anchorage blocks are used to mitigate errors in length of PWS type stay cables.