Разработка алгоритма расстановки меток для решения задачи сетевого планирования в условиях нечеткого компромисса типа «Время-затраты»

Берштейн Леонид Самойлович, Князева Маргарита Владимировна · Известия Южного федерального университета. Технические науки · 2011

The sub problem of fuzzytime-cost trade-off is considered. A direct activity cost function is used, which is assumed to describe the complex interaction between the activity duration and the required resources. The optimization subject to criterion time-cost is performed with a help of flow in the net-project graph, the algorithm of labeling is examined up to the stated problem, the essence of proposed labeling algorithm is to iteratively calculate a sequence of less and less cheap cuts in the current network of critical activities by which the project duration is reduced.