Optimal short-term thermal unit commitment
C.K. Pang, H.C. Chen · IEEE Transactions on Power Apparatus and Systems · 1976
Fuel cost savings can be obtained by proper commitment of the available generating units. This paper describes a truncated dynamic programming method for the commitment of thermal units over a period of up to 48 hours. The commitment is such that the total cost is minimal. The total cost includes both the production cost and costs associated with the startup and shutdown of units. The startup cost for each unit is dependent on the amount of time the unit has been shutdown prior to startup. A variety of spinning reserve requirements are observed and crew constraints on the startup and/or shutdown of two or more units in the same plant are imposed on some of the plants. In addition, operation of individual units must satisfy the specified minimum up times and minimum shutdown times.
Cited by 218 works. doi:10.1109/t-pas.1976.32228
Authors
References
- Economic operation of power systems
- Review of load-flow calculation methods
- Generating Unit Commitment by Dynamic Programming
- Some applications of optimization techniques to power systems problems
- Large Scale Hydro-Thermal Unit Commitment-Method and Results
- A Study of the Economic Shutdown of Generating Units in Daily Dispatch
- An Application of Mixed-Integer Programming Duality to Scheduling Thermal Generating Systems
- Security Constrained Unit Commitment
- Optimal Thermal Generating Unit Commitment
- Unit Commitment