용인 경량전철시스템 건설관리 단계별 문제점 도출 및 해결 방안 연구
연상호, 김학두 · 한국철도학회 학술발표대회논문집 · 2009
For the implementation of Light Electric Railway Transportation System(LRT) at he Yongin city area as the first time on 2005, Daelim Industrial co, Ltd. and Bombardrier co, Ltd. were participated as consortium type. Its known to high technology about railway system and operation areas. The aim of this study is to verify for performance of some problems extraction and, solutions with consortiums for project preparation and process about each item and steps of LERS. Also we extracted and analysis of some complicit problems at the bidding and contract stages, design management, permissions for government, process management, contingency management. As the results of this study, this project needed more time and budgets for preparation between daelim and bombardier for the good solutions and process management, especially construction and process management stages were extraction many design changes and complicates for the better solutions and project implementations. So, we suggested the various solutions for the successful agreement and answer for LRT.
Cited by 0 works.