設計變更에 의한 工事金額의 영향에 관한 硏究

임칠순, 이규철 · 대한건축학회 논문집 - 구조계 · 2004

Until now a problem between the standard ordering ruler and constructors which is held in its arms, and result construction cost is calculated at being strong, and occur in an ordering process by increase of the amount of resources, decrease, a drawing alteration has been untied in a lot of public institutions from 1970. A local public institution analyzed profit and loss of construction cost by a design change during construction in 0 buildings for 2001 years. Cost is 170,989,000,000 won with 387 cases, and a total ordering number is with design change number total 266 cases among this, and decrease is 2,009,000,000 won with 48 cases in 16,705,000,000 won with 218 cases increase 23.13% (464,000,000 won), loss occurred with 12.42% (249,000,000 won) the profit that occurred in an enforcement document of construction cost during decrease contents.