중수로형 원전의 안전관련 설비 경년열화 관리계획 평가
정성규, 김현수, 진태은 et al. · 대한기계학회 춘추학술대회 · 2009
In order to investigate the feasibility of continued operation of CANDU nuclear power plants, the evaluation for the aging management plans(AMPs) has been accomplished being based on the law for continued operation of the domestic nuclear power plants. Total 38 AMPs, presented in MEST Notice 2008-17, were evaluated according to the reference standards such as USNRC guidelines, CSA Code of Canada, and IAEA technical documents, etc. As a result of the assessment, it was thought that 5 items including the onetime inspection should be established and implemented before the continued operation. In addition, the establishment and execution of aging management plans for 6 items including the flow-accelerated corrosion (FAC) was necessary. In conclusion, the continued operation of a CANDU nuclear power plant is possible if aged major components are refurbished and these recommendations are implemented.
Cited by 1 works.