기후정보를 이용한 공동주택 건설공사의 비작업일 산정에 관한 연구
방종대, 손정락, Sang-Hun Song et al. · 대한건축학회 학술발표대회 논문집 · 2014
Non-working day is one of the biggest factors contributing to the project schedule and relation to the construction duration. Even though project scale is same, non-working day may be increase or decrease depending on the local weather elements. But, accuracy of construction duration is low because many companies calculate the construction duration using the past data or experiences and they are not consider the weather conditions of the regions. So, this study calculated the regions non-working day of the apartment construction work using the weather elements, five work days week, public holiday.