Until now, in architectural project, selection method for construction-method has been excuted by decision making of some technical experts dependent on their experience and intuition. As a result, there have been frequent construction-method alterations during th e construction process and delay of duration, addition of cost, etc have followed accordingly. As this the case, there is a need for an appraisal tool and verification for the selection of rational retaining wall bearing Methods. In this research, we have studied about selection method for optimal construction-method through constraint analysis. The process of this research of following 4 steps. 1) construction method's selection by soil conditions 2) construction method's selection by safety evaluation 3) construction method's selection by construction conditions 4) construction method's selection by cost comparison.