공동 주택 공사시 작업 분석을 통한 철근공사 개선 방안

김범중, 신한우, 이웅균 et al. · 대한건축학회 학술발표대회 논문집 - 구조계 · 2006

The installation of rebar constitutes a major portion of framework of cast-in-placed concrete structure. Although reinforcing steel occupies a small portion of the volume of reinforced concrete structure work, its contribution to the cost is approximately equal to that of concrete. However, rebar work in the framework is done by hand at job site and it can lead to a decline of the construction productivity. Therefore, in this study, a work monitoring method called work sampling and crew balance study is proposed that to improve labor productivity of rebar work and present a new work sequences. In order to develop work methods, we observed a wall frame. As a result of this observation and analysis, rebar pre-fabrication method and revised work sequences is suggested to improve work efficiency. Using this observation data, not only improving work productivity, but also cost saving of concrete framework and shortening the work duration could be possible.