장대 철도터널의 정량적 안전성 분석 사례 검토

김성용, 문재석, 이양상 et al. · 한국철도학회 학술발표대회논문집 · 2010

Although Railway system demands very high safety measurement, a construction of long tunnel which is hard to achieve safety securement requires proper disaster prevention plan. In the phase of basic design Baegun-tunnel and Parkdal- tunnel runnning 14km and 11km seperately as a long railway tunnel, which is located on the line of the Joungang line(wonju-jechun line), was designed as double-bore single track tunnel. However, we can also conclude that construction of single-bore double track tunnel not only meets social risk criteria by the result of a quantitative risk analysis of long railway tunnel based on 'rail safety standards relating to the rule' but also is expected to save approximately 1700 million won annually.