모듈러 건축공사의 타워크레인 위치 및 건축물 배치 도식화 방안

이두완, 박문서, 이현수 et al. · 대한건축학회 학술발표대회 논문집 · 2016

For the completion of the modular building, it is necessary to move the modular unit to the installation position for lifting. This is the largest part in the field work of modular construction. If lifting plan is not appropriate, leading to an increase the construction time and cost, reducing the shortening effect that is an advantage of the modular construction. Therefore, in this study, to suggest the diagramming solution of the position of the modular building and the position of T/C should be considered in the mid-to-high-rise modular building construction of the inner city. This can be used for the previous studies for the optimum arrangement of locating of the T/C and deduction of the possible location of modular unit in High-rise modular construction with consideration of the High-rise modular field conditions.