Техническое перевооружение кольцевой печи
А. А. Чапурина, Е. В. Киселев · Electronic scientific archive of UrFU (Ural Federal University) · 2017
The design and thermal operation of a ring furnace for heating pipe billets before rolling are considered. The calculation of the heating of metal is made and the thermal balance of the operating furnace is compiled. According to the received data, the main drawbacks of the design and heat work are revealed. Measures are proposed for the technical re-equipment of the furnace in order to reduce fuel consumption and increase productivity: replacement of brick lining with fibrous, use of high-speed burners, use of not water-cooled partitions. To better assess the positive impact of the proposed activities, a new heat balance was drawn up. The work of the furnace after modernization has been analyzed, new indicators of heat work have been determined. When implementing the proposed technical re-equipment, a significant economic effect is expected, an improvement in the quality of metal heating, with a reduction in fuel consumption and an increase in unit capacity.
Cited by 0 works. Open-access PDF