The article considers two variants of arrangement freightdelivery of slags in the «Eastern» open pit using railwaytransport. It is proposed to use railway dumping in thetechnical stage of reclamation. The calculation of economic indices of the «Eastern» open pit reclamation isperformed. The use of railway transport, to reducetransport costs, contributes to the achievement of maximum economic effect from the use of the worked out pit’sarea and dumps of overburden rocks, formed as a container for disposal of industrial pit’s wastes and dumps forplacement metallurgical production wastes.