Оптимальное распределение мощностей между генераторами электростанций промышленного предприятия при длительном пофазном ремонте оборудования питающих сетей
Малафеев Алексей Вячеславович, Кочкина Александра Владимировна, Панова Евгения Александровна · CyberLeninK (CyberLeninka) · 2012
The algorithm of local industrial power plant generators load optimization in terms of 500 kV bulk transmission substation autoconnected transformer continuous single-phase scheduled-outage taking into account generating equipment heterogeneity, power losses in distribution system, limitation of negative-sequence and phase current in generator stator wind. The combination of successive reduction and symmetrical components methods is used for single-phase operating conditions computation. Combination of successive reduction and dynamic programming methods is used for optimal generators load computation.
Cited by 0 works.